Lafarge Zementwerke GmbH - Retznei site
De- und Montage der Elektrofilterkammer 1
Disassembly and reassembly of the electrostatic filter chamber 1
- Disassembly of the existing filter ceiling
- Disassembly of the existing steel construction (catwalks)
- Production and assembly of the new catwalks
- Replacement of the electrostatic filter panels and electrodes
- Installation of the new filter ceiling
Material: S235JR
Steel construction: 10 to
Activity
Production, AssemblyProject location
Austria, RetzneiTiger Coatings GmbH & Co KG
Steel construction plant
Static calculation, planning, production and assembly of a new steel construction plant for Tiger Coatings
Dimensions: L 19.1 m, W 14.9 m, H 11.7 m
Total weight: approx. 80 to